FAIR HARBOR BEACH EROSION CONTROL DISTRICT - August
2001 Status Report
The Fair Harbor Beach is in poor shape. At high tide,
there is little or no beach, with water coming up to the newly installed
dune fencing. Much of the sand deposited during our previous 1994
replenishment is gone. We are greatly concerned that a severe winter could
yield further erosion and the possible loss of homes.
Planning and permitting for another replenishment is well
underway. Fair Harbor, Dunewood and Saltaire signed a contract in mid June
with Coastal Planning and Engineering (CPE) to prepare plans, seek
permits, and oversee a second replenishment. CPE managed our last
replenishment and has been doing our annual beach monitoring. CPE has
subcontracted the seeking of permits to Land Use Associates (LUA), another
firm that we have used previously.
CPE will come to the community to present its draft plan
for replenishment on Sunday, September 16. This will provide an
opportunity for Fair Harbor residents to ask questions and comment on
possible changes. After the three communities are satisfied with the plan,
LUA will submit permit applications to execute the plan to various Federal
and State agencies, including NYS DEC, and Fire Island Seashore. When cost
information becomes available, hopefully this fall, we will seek approval
from the community to issue bonds and proceed with the actual
replenishment. LUA expects that it will take approximately one year, from
the time of application, to obtain all permits. We are exploring possible
ways to speed this. Following obtaining permits and financing, the
replenishment will proceed as soon as possible consistent with CPE advice,
environmental considerations, and what weather permits.
Frequently Asked Questions
Q. The beach is in terrible shape. Why is this
all taking so long?
A. A number of factors contribute to delay.
1) The need to follow competitive bidding processes in
selecting contractors, which entails writing a Statement of Work,
soliciting bids, reviewing proposals and selecting a winner.
2) Need for the three communities, Saltaire, Dunewood, and
Fair Harbor to agree on contractor, contract, and project details. Project
urgency is not uniform across the three communities. A number of months
were spent negotiating and finalizing the contract to a point where it was
acceptable to all communities.
3) Permits take time to obtain. A number of agencies
overlap in jurisdiction over our project. Our contract with CPE explicitly
lists permits from the NYS DEC (Article 25 Tidal Wetlands); NYS Department
of State - Coastal Consistency Certification; US Army Core of Engineers;
NYS Office of General Services (Borrow Site Authorization); National Park
Service Special Use Permit for sand deposition on Federal lands if
applicable; National Park Service - Construction equipment access points
for project implementation. Some agencies routinely circulate permit
applications such as ours to other
agencies (for example Fish and Wildlife) for comment.
These other agencies can request further information. Although we believe
that most agencies will respect the need for our project and its
urgency, some agencies assign low priority to property preservation or are
reportedly not likely to be supportive of our project.
4) The replenishment must be timed with environmental
concerns, availability of equipment, and weather.
We are exploring ways to speed permitting, but if the LUA
estimate holds, we will not have permits to proceed until fall of 2002.
Q. How much will the project cost and
how will it be paid for?
A. Permitting and project management will cost
approximately $180,000 of which Fair Harbor’s
share will be approximately $61,000. This will be paid from funds left
over from our last replenishment. Sand deposition cost will depend on
borrow site selection, and ability to share equipment mobilization cost,
which is a significant fraction of the total. We expect to have cost
estimates from CPE this fall. The sand deposition will be paid for by a
bond issue, where the principal and interest will be paid for by property
taxes by the Fair Harbor Beach Erosion Control District. Since current
bond payments extend through 2003, we anticipate a one or two years
overlap period during which will be paying for both the last and current
project.
Q. Are any other costs expected?
A. It is possible that there will be additional
money. Both permitting and replenishment are subject to uncertainties. For
example, we do not yet know if we will be required to prepare an
Environmental Impact Statement or whether any legal fees will be required
in obtaining permits. We expect that these costs, if necessary, will be
small relative to the actual sand deposition.
Q. How did we choose to join with Saltaire and
Dunewood? Are more communities interested?
A. We are joining with Saltaire and Dunewood to
save costs and obtain a more effective project. We have previous
experience with these communities; they are ready to proceed, and have the
infrastructure to pay. We would be happy to add additional contiguous
areas, provided that they do not cause delay. Ken Cohen, the Dunewood Dune
District Commissioner, has contacted other communities within Islip, but,
to date, none has come forward to join. Our CPE contract allows other
communities to join and has provision for cost sharing, but this must
happen soon.
Q. How will cost be apportioned amongst the
three communities?
A. Planning and permitting costs are being
apportioned according to lineal feet of beach possessed by each community.
Based on this, Saltaire will pay one half, Fair Harbor one third, and
Dunewood one sixth. Apportionment of the payment for deposited sand has
not yet been decided.
Q. How did we pick CPE to plan and oversee our
project?
A. An initial list of seven firms was formed based
on attendance and presentations at beach erosion conferences over a
several year period. A Statement of Work was written and each of the seven
firms was invited to submit a proposal and bid for our project. Three
firms responded. Of the three, the CPE proposal was by far the most
attractive based on price, familiarity with our beach, and familiarity
with studies done for the Interim Project. CPE will use these Interim
Project studies as much as possible for our permit application. We have
had positive experience with CPE in our previous project and our annual
beach monitoring.
Q. The Fire Island Inlet is dredged
periodically. Can we take advantage of the periodic visitation of the
dredge to save mobilization cost?
A. We will try. CPE’s
advice is to focus on getting permits and financing as soon as possible
and then look for opportunities to save on costs when we have a date at
which we will be ready. We can then see what equipment mobilization
sharing opportunities are available. CPE cautions that sharing may require
delaying our project to synchronize with another and may not be
worth it.
We are also planning to explore periodic maintenance
synchronized with dredge visits. However, periodic maintenance requires an
open ended permit, which CPE advises is much harder to get, entailing more
scrutiny and delay by the various agencies than a one time permit. Because
of the urgency of our situation, CPE advises that we initially seek
a one time permit to get some sand on the beach as soon as possible, and
then follow up with an application for an open ended permit if we seek to
do periodic replenishment.
Q. Where are we going to get the sand?
A. Our CPE contract involves investigation of two
potential borrow sites. One of these is an area some distance off the
coast of Cherry Grove, which was used in our previous project, and was
also proposed in the Fire Island Interim Plan. A second nearby borrow site
exists off of Saltaire-Fair Harbor, which may allow cost savings because
its nearby nature allows an economical dredging process, but it may not be
usable.
Q. What is contained in our annual beach
monitoring and how can I see the report?
A. Annual monitoring is performed by CPE each fall
and a report is produced giving the onshore and off shore sand profiles
taken every few hundred feet from Dunewood to Saltaire. CPE calculates the
amount of sand lost and remaining relative to our original 1994 project
and makes a recommendation on any needed action. Until 1999, our beach was
in good shape, with many areas having even more sand than after the 1994
project. CPE believes that this was because of a large aggregation of sand
that moved down the beach from east to west following the 1992/93 storm.
Recall that Lonelyville and Dunewood beaches were very wide during the
1994 - 96 period. Since then, the aggregation has passed, and sand amounts
have moved back to normal. Until 1999, there was little to report from
beach monitoring, other than the positive state of the beach. The November
1999 report, however, revealed that Dunewood and eastern Fair Harbor had
lost a great deal of sand, especially offshore. CPE recommended that we
consider seeking permits for a possible replenishment, because they would
take at least a year to obtain, would be good to have, and would not cost
too much. This was reported at Fair Harbor Community Association meetings
during the spring of 2000 and planning for a replenishment project was
initiated.
The CPE monitoring reports fill a small loose-leaf binder
and are too voluminous for community wide mailing. Because of heightened
interest, we will reproduce a number of copies, which we will be available
for loan from members of the FHBECD Committee. We will continue to provide
summaries in community mailings and at FH Community Association meetings.
Q. How did our 1994 replenishment project
perform? Did we expect that we would have to do this again in eight to ten
years?
A. The 1994 project has performed close to the CPE
prediction. In 1993, CPE predicted that approximately 95% of the sand
would be gone in ten years. Performance has been uneven. The eastern
portion of the project area in Dunewood has lost virtually all of the
original sand volume, whereas the western part in Saltaire still has much
of the original sand volume. This is to be expected. CPE has indicated
that a project in our area is likely to fail first in the eastern portion.
Although residents tend to focus on the beach and dune,
which is the sand that is visible, much of the CPE focus is on the sand
volume immediately offshore, which is much larger, and which ultimately
governs onshore processes. The 1999 beach monitoring report revealed the
heavy sand loss offshore in Dunewood, which was subsequently followed by
rapid erosion of the on-shore beach and dune during 2000 and 2001.
Q. In view of how long this is taking, why didn’t
we start earlier?
A. Beach monitoring reports and visual
inspection of the beach did not show need for a project in 1998 and
earlier. Support for spending tax dollars for replenishment was not there.
As soon as the need and community support for replenishment became
evident, the planning process was initiated.
Q. Can we declare that this is an emergency to
speed permitting?
A. Formal emergency declaration requires the
President of the United States. We have not yet experienced the loss of
life or property to support this. CPE has already taken photographs of
some homes at risk to be used to make the case of the urgency of our
situation in the permitting.
Q. What happens next? Is there anything that
the community can do to help?
A. CPE will come to Fair Harbor to present its
draft proposal on Sunday, September 16. There may be options affecting
project cost, risk, appearance, and time frame that we will need to decide
rapidly. We are working with the Town of Islip in preparing the necessary
bond issue. When costs become available, we will need an indication that
Fair Harbor homeowners support the project. After permit applications are
submitted with the finalized plan, members of the community will need to
contact elected representatives to generate support. Expect to hear more
on this at the appropriate time.
Erica Fried, FHBECD Deputy Commissioner
Frank Burns, Jerome Feder, Nevio Maggiora, Wells Newell,
Claire Walsh, Committee Members |