FAIR HARBOR BEACH EROSION CONTROL DISTRICT
UPDATE ON REPLENISHMENT PROJECTS SEPTEMBER 30, 2001
FHBECD, in cooperation with Saltaire and Dunewood, is
pursuing several alternative or complementary projects to get sand on our
beach as soon as possible.
1.
Off-shore dredging.
Coastal
Planning and Engineering (CPE)
presented alternatives for moderate or large replenishment
projects. Costs are estimates.
| Project |
Total c.y, |
FH c.y. |
Cost per House
per year |
| 1994 Project 10yr bond |
465,000
|
179,000
|
$550
|
|
Future project estimates |
|
|
|
|
Moderate/Close borrow site
|
834,000
|
233,000 |
$585
|
|
Large/Close borrow site |
1,300,000 |
375,000 |
$855 |
|
Moderate/Far borrow site |
834,000 |
233,000 |
$1,036
|
|
Large/Far borrow site
|
1,300,000 |
375,000
|
$1,576 |
|
Trucked sand
|
15,000
|
5,000
|
$160 |
Note that the moderate size project would give
us more sand than the 1994 project. If we can use the close borrow site,
the cost is only slightly higher. The far borrow site would be much more
expensive. Estimates assume 7 yr 4.5% bond, 370 homes., Lonelyville
participation. Final price and sand volume subject to recent survey and
actual price quotes.
2. Fire Island Inlet Sand
We requested use of sand from Army Corps of Engineers (ACE)
periodic dredging of Fire Island Inlet. We have not received the
official response from ACE. NYS Department of Environmental Conservation
(DEC) indicated a policy
against placing the sand East of the dredge site, except to Robert Moses
State Park. However, they indicated that we could dredge from the inlet at
our expense. Because of the increased distance between the beach and the
borrow-site this alternative is more expensive than off-shore dredging,
unless the ACE assumes part of the cost. Investigation of FI Inlet sand is
continuing.
3. Trucking sand from Democrat Point.
The sand may be available, and “free” although we may be responsible for
replacing it. We need permits from NYSDEC, NYSDOS, LI State Park
Commission, Fire Island National Seashore and possibly other agencies. We
were told by DEC that there is no specific definition of “emergency”
required. Disturbingly, the National Park Service is strongly opposed.
Estimate for permits without environmental impact study was $2,350 for FH.
As background, in 1994 we (FH, Dunewood and
Saltaire) trucked ~12,000 c.y. at $18/ c.y., partly paid by the
communities and in part by property owners. C. Bowman recommends against
trucking sand onto an eroding beach. If we elect to truck sand and place
2.5c.y./ft along the dune face to stabilize the dunes, we would get
5,000c.y. at $12 per c.y. or $60,000.
It may be possible to get a cheaper contractor, however.
As background, note that erosion in FH was
~39,000c.y. Oct. 1999-Oct. 2000. Trucking capacity is 900c.y./day, making
large volumes impracticable, as well as very expensive.
Proposed Directions
1.Permit for large project, since it does not require doing the large
project, but increases our options.
2. Proceed with permit application for Democrat Point
Sand. Can proceed with permit application, but stop at EIS. If the
condition of the beach is declared to be an emergency, we may be able to
truck in sand to save homes and stabilize the dunes without the EIS. If
emergency is declared, we may also speed up permit process for dredging.
3. Continue investigation of FI Inlet sand.
Erica Fried, Deputy Commissioner, Frank Burns, Jerome
Feder,
Nevio Maggiora, Wells Newell, Claire Walsh,
FHBECD Committee |